Conservation Approval Process

For New Construction or Additions - Under Revision

Responsibility

Activity
Applicant1. Complete the Request for Conservation Site Inspection form. This form is also included in the Building Inspector package.

Applicant

2. Submit the completed form to the Building Inspector with other required forms.

Building Inspector

3. Will review forms, determine whether Conservation Commission inspection approval is required by law. Confer with Conservation Commission.

Conservation Commission

As determined necessary by Building Inspector and Conservation Commission and required by Massachusetts Law:

4. Schedule and conduct a site inspection with Applicant

5. Post Notice of Public Hearing.

6. Conduct Public Hearing

7. Determine legal requirements

8. Make determination on the application.

9. Communicate in writing about the determination to the Applicant, Planning Board and Building Inspector.