The Make Ready Estimated Completion Date (ECD) is Q3 of 2021. Construction by Comcast ECD is Q3 2022.
Eversource and Verizon have received all survey payments and they are conducting pole surveys and estimations. MBI’s contractor will provide additional reconciliation once the preliminary designs are received from the utilities.
The work on Schoolhouse Road is about 2/3 complete and will resume in the Spring